Village Manager Mary Beth Murphy's update on the Main St. and Warburton Ave. Paving Project July 29, 2022 Update

MB MURPHY
seal
Village of Hastings-on-Hudson
Village Manager

Main St. and Warburton Ave. Paving Project July 29, 2022 Update

As many of you know there has been much concern expressed about the removal of 13 trees on Main Street & Warburton Ave. The Village certainly did not take this decision lightly but considered the long-term health of the trees and the need for pedestrian safety and passable sidewalks.  Unfortunately, the existing tree pits are too cramped for the roots of the trees they currently hold. They will be replaced with larger tree pits with inset grates and permeable hexagonal paving stones to allow for water infiltration and walkability.  Replacement trees will be native species suitable for downtown planting.
MAINST1
 
Above is a photo of a tree on Main St. with what is known as "girdling roots" where the roots begin to wrap around the tree itself rather than radiating out in a healthy fashion. Girdling restricts the movement of water and puts pressure on the trees. Constricted tree pits deny the trees’ root systems sufficient water and oxygen, and the trees eventually end up in effect strangling themselves and dying (see here for more information on this phenomena: https://www.arborrangers.com/girdling-roots-kill-trees/). 
 
Planting trees in small planting holes is a common cause of girdling, and the issue is exacerbated when planting holes are surrounded by inflexible concrete or paving. There’s nowhere for the lateral roots near the surface to go, so the natural flaring at the base of a trunk is compressed. Roots meant to grow laterally hit the inflexible edge of the planting hole and change their direction to circle around in the limited volume of open soil. Urban street trees are common victims of this, as their planting holes are notoriously undersized. The longer a tree must deal with girdling roots, the weaker and more unstable it becomes. If you walk through our downtown, you will see many examples of this destructive girdling process.
 
One of the side effects of girdling is that the trees lift up the sidewalk slab (there are also many examples of this in the downtown) creating tripping hazards for pedestrians, and the uneven surfaces are difficult to navigate, particularly for pedestrians using walkers, shopping carts, pushing strollers and other wheeled conveyance.  It is particularly problematic in municipalities like ours where the sidewalks are very narrow. 
 
If left unresolved, the conflicting root(s) may eventually choke and strangle the plant, interrupting the uptake of water and nutrients completely in the girdled zone, which, in turn, leads to:
  • plant decline
  • attracting wood-destroying organisms
  • premature fall color of foliage
  • defoliation
  • dieback of xylem, cambium, and phloem layers
  • loosening and detachment of outer bark
  • dieback of twigs, branches, and stems
  • high-risk severe dehydration during droughts
  • and may eventually kill the entire plant.
 
As part of the sidewalk project the tree pits will be enlarged and modified to better accommodate a healthy growing environment for trees.  In addition, the choices of trees and method of planting will be tailored to a street tree environment. The tree pits will also allow for both water infiltration and walkability across them with pavers.
 
The demolition and reconstruction of the sidewalks will be done in small tranches of 70 to 100 feet to reduce disturbance in the downtown.  Having prepared the site the Contractor has set up a staging area at the Steinschneider parking lot, dug test pits, located electrical lines and is currently excavating and installed conduit and new pull boxes on Main Street.
 
MAINST2
This photo shows the contractor at work on the corner of Main St. and Warburton Ave.
 
The schedule anticipates work in the area from Warburton Ave to 8 Main St at Hastings Own Bagel from July 27- Aug 1st  including demolition, followed by placement of forms and  pouring of concrete for the new sidewalk.
Absent unforeseen issues, from Aug 2nd to Aug 5th similar work will occur between 8 Main St and 14 Main St (Slices Pizza Shop).
The contractor will provide access ramps for all residential and business entrances.
Street parking may be affected and notice to the public will go out in advance for the locations affected. 
 
MAINST3
MAINST4

Above are photos of the demolition work in front of Hastings Own Bagel and Chelsea Dry Goods.

MAINST5
This photo shows accessibility to Hastings Own Bagel.
 
MAINST6

This photo shows accessibility to Chelsea Dry Goods.

MAINST7
Photo shows staging area in Steinschneider lot.
The spaces are located directly across from the charging station.
 
Regards 
MBMURPHY
Mary Beth Murphy
Village Manager
office: 914.478.3420
cell: 914.384.0616
 
 
 
 

CLICK HERE TO "TELL IT TO VILLAGE HALL"

Village of Hastings-on-Hudson
7 Maple Ave, Hastings-on-Hudson, NY 10706
web:    http://Hastingsgov.org              
STAY CONNECTED! DOWNLOAD ALL OF OUR SMARTPHONE APPS HERE
    fb       twit      i
SIGN UP FOR TEXT ALERTS AT: http://hastingsgov.org/subscribe-text
For information regarding access for persons with disabilities, please visit http://hastingsgov.org or call 914-478-3400.
 WHoH-TV is on facebook with links to all current meetings & events!  Streaming live at WHoH-TV.org
The Hastings-on-Hudson Technology Department asks that you consider the environment before printing this e-mail.