UPDATE: Ravensdale Bridge - June 13, 2021
More than half poured:
Here’s a view from the east end. The green steel reinforcing rebar (“reinforcing bar”) is yet to be covered. Note concrete pump extending over bridge:
Workers spreading concrete after it’s been poured:
As of June 5, the entire roadbed had been poured, as well as the sidewalks on top. The green rebar turned up at the right will reinforce the parapet walls. Between the rebar and the plywood formwork, Styrofoam forms can be seen that will leave the false arch impressions in the face of the parapet walls:
Here is a closer view of the Styrofoam formwork as well as the beginnings of the rebar cage to support a lamp post—electrical conduit can be seen snaking up:
Here is completed formwork with a rebar cage to support a lamp post--the three vertical wood strips at the back of the cage will be vertical ornamental indents in the final concrete pour, and the green rectangle to the left is protection over an access panel to the electrical box:
- May: Completion of Bridge Substructure
- Now: Completion of Bridge Superstructure, Utilities, Roadway and Approaches & Opening of New Ravensdale Bridge to Traffic
- August: Removal of the Temporary Bridge
- October: Completion of Roadway Reconstruction and Landscaping