qApril 1994: Riverkeeper
initiates lawsuit to require ARCO to address PCB contamination on
the site.
qMay 1994: Hastings joins lawsuit.
qMay 1995: Case suspended while DEC
investigates.
qMarch 2001: Judge denies
motions that would dispose of case without trial.
qJanuary 2002-April 2003:
Riverkeeper, the Village and ARCO engage in intense three-way
settlement talks.
qFall 2002: Judge sets trial date for May
2003.
qApril 2003: Parties sign
Term Sheet of Proposed Settlement.